After you configure and save a workload migration, you can modify the time and pattern to run incremental replications that occur after the first replication. You can alternatively start each incremental replication manually. See Starting Incremental Replications.
NOTE:
Scheduled incremental replications are skipped until the first full replication is complete.
Scheduled incremental replications take place for a maximum period of 60 days from the time that the scheduled incremental replication runs begin.
To schedule the incremental replication recurrence time and pattern:
On the Workloads page, locate and click the workload.
On the Migration Details page, click Edit.
On the Edit Migration Details page, go to Schedule Settings > Incremental Recurrence, then click Edit.
The default Incremental recurrence setting is None. The incremental replications are unscheduled.
For Begin the recurrence schedule, set the date and time when you want to begin the scheduled incremental replications.
You can type the date (dd/mm/yyyy) or click the Calendar icon to select the date. The default run time is 12:00:00 a.m. (hh:mm:ss a.m. or p.m.).
For Recurrence run setting, set the pattern to follow for scheduled incremental replications:
Daily: The replication takes place on the specified daily intervals or on weekdays every week for a period of 60 days from the time the replication starts.
Weekly: The replication takes place at specified intervals for a period of 8 weeks from the time the replication starts.
Monthly: The replication takes place at specified intervals for a period of 2 months from the time the replication starts.
Click Close to return to the Edit Migration Details page, then click Save.