After the migration preparation completes successfully, the migration is ready for execution. Execution begins with the first replication, which might be a full replication or a data synchronization for a pre-existing target workload.
The default schedule setting is None. The first replication is unscheduled. You can schedule the start date and time to run the first replication. You can alternatively start the first replication manually. See Section 34.2, Starting Migration Execution (First Replication).
The first replication for a scheduled migration execution is a one-time event, but the run is attempted daily as scheduled until the first replication begins and completes successfully.
NOTE:You must prepare the workload prior to the scheduled time or the manual start. The first replication cannot run unless the target workload exists and the workload preparation is complete. If they are not ready, Migrate skips the scheduled replication and retries it at the scheduled time on the next day.
To modify the start date and time for the first replication:
In the Jobs view, locate the required job.
Right-click the job and select Change Start Time to open the Change Job Start Time dialog box.
Specify the required start date and time, then click OK.
PlateSpin Migrate reschedules the job and executes it at the specified time.
To modify the start date and time for the first replication:
On the Workloads page, locate and click the workload.
On the Migration Details page, click Edit.
On the Edit Migration Details page, go to Schedule Settings > Full Replication, then click Edit.
Click Start, then set the date and time when you want to start the first full replication.
You can type the date (dd/mm/yyyy) or click the Calendar icon to select the date. The default run time is 12:00:00 a.m. (hh:mm:ss a.m. or p.m.).
Click Close to return to the Edit Migration Details page, then click Save.