Task Properties

This topic presents the task properties and their descriptions as displayed in the Task Properties dialog box. The Task Properties dialog box contains the following tabbed pages of properties.

Task

The following properties are on the Task tab.

Subtask Of
Displays the name of the task for which this item is a subtask (if this item is a subtask).
Name
Displays the name of the task or subtask.
Responsibility
Displays the name of the person responsible for the completion of this task or subtask. Other people can be assigned as additional resources.
Milestone
Indicates that the task or subtask should be treated as a milestone.
Status

Displays the task status:

Pending
Waiting for completion of a predecessor task.
Ready To Start
Work can be started on the task.
In Progress
Work has been entered for the task.
Finished
Work is finished on the task.
Closed
Task is completed and closed.
Hold
Work temporarily stopped on the task, usually to wait for completion of another task.
Priority
Displays the task priority level. The default is Medium. These priorities are identical to those in MS Project. Do Not Level is a Microsoft Project-specific term you should ignore.
Duration
Indicates the number of hours expected for completion of the task.
Percent Complete
Displays the percentage of work that has been completed on a task.
Needs Attention
Notifies team leaders or task reviewers that this task requires attention. Enter the information about why this task needs attention in the text box below the Needs Attention check box.

Resources

The Resources tab lists the task resources. You can assign responsibility to team members by adding them to the list with the Add button, and you can remove them using the Remove button.

Time

The following properties are on the Time tab.

Plan Start
Displays the start date for the task.
Plan Finish
Displays the finish date for the task.
Plan Work
Indicates the number of hours estimated to complete this task.
Actual Start
Displays the actual start date calculated from work record entry.
Actual Finish
Displays the actual finish date task status changes to Finished.
Actual Work
Indicates the actual number of hours taken to complete the task, calculated from Work Records.
Variance Start
Displays the variance in days between expected start date and actual start date. This is read-only calculated value.
Variance Finish
Displays the variance in days between expected finish date and actual finish date. This is read-only calculated value.
Variance Work
Displays the variance in number of hours between estimated and actual duration. This is read-only calculated value.

Work

The Work tab lists all the work records entered for this task. Each work record has the following properties.

User Name
Displays the name of person who performed the work for this work record entry.
Date
Displays the date of work record entry.
Work Hours
Indicates the number of hours worked for this work record entry.
Remaining Work
Indicates the remaining number of hours left to complete the task.
Comments
Displays text comments explaining what work was done for this work record.
Total Actual Work
Displays read-only calculated field of the total time spent on this task based on the work records entered.

Notes

The Notes tab is a simply a text box for capturing notes about the task.

Custom

You can create custom properties for an item which will display in the item Properties dialog box.

The following properties are on the Custom tab.

Property
Displays each custom property name.
Value
Displays the values for each custom property. Double-click the property name to edit the value.

Attachments

The Attachments tab contains a list of all the files attached to the current item.

Comment

The following properties are on the Comment tab.

Comment For This Revision
Displays the reason for the changes to the current revision.
Comment For New Revision
Displays the reason for the changes to the new revision.