Activating or Deactivating Projects and Project Baselines
Note: You can also activate or deactivate an existing project or project baseline from the
Project List page. For additional infomation, see
Editing Projects.
To activate or deactivate an existing project or project baseline:
In the menu, click
Projects
> Project List
.
The
Projects page displays, listing all existing projects and project baselines.
Click
Active/Inactive in the
Status column of the project or project baseline you want to activate or deactivate.
A confirmation dialog box displays, asking you if you are sure about the activation or deactivation.
Confirm to toggle the project status to
Active or
Inactive.