You can modify the following settings for the workload transformation after you submit the workload without needing to withdraw it:
Transformation Plan
Wave
Batch
Start Date and Time
Cutover Date and Time
On Hold
Transformation History
User-provided notes
To modify the plan or add a note for a single workload:
In the Web Interface, select the project in the Global Project Selector.
Select Planning in the toolbar, then select the Workloads tab.
Use the Filter and Advanced Search options to locate the workload of interest.
Double-click the workload you want to modify to open its Workload dialog. You can alternatively select the workload, and then click Edit.
In the Transformation Plan panel, click Edit, then modify the schedule information as needed.
In the Transformation History panel, click View, then add notes as needed.
Click Close to exit the Workload dialog.
To modify the plan of one or more workloads using Bulk Edit:
In the Web Interface, select the project in the Global Project Selector.
Select Planning in the toolbar, then select the Workloads tab.
Use the Filter and Advanced Search options to locate the workloads of interest.
Select the specific workloads you want to modify.
Click Bulk Edit.
(Optional) Modify the plan settings as needed:
Wave
Batch
Remove from Batch and Wave
Start Date
Cutover Date
On Hold
Click Apply.
Review the change confirmation, then click Proceed.
Workloads dimmed in an On Hold state are dimmed in the Workloads list.