In the Web Interface, select Planning in the toolbar, then select the Batches tab.
Select one or more batches from the list that you want to move to a different wave. The batches can be in the same or different wave. Press Shift and click the appropriate batches to select multiple batches.
Click Move.
In the Move dialog, select the appropriate destination wave, then click OK.
If there are date conflicts between the dates set for the batches and their new parent wave, specify your preference for how you want to handle the dates.
For example, you might choose to allow the batch dates to change to fit into the window scheduled for the new parent wave, or keep the existing dates and fix them later. Conflicted dates display in a red font.
If the batches’ dates are inherited, the batches automatically inherit the dates from the new parent wave.
Click Save.
Click Close.