28.5 Associating Migration Servers and Target Workloads

After you create Migration Server resources for a project, you can associate them with workloads. You can specify the Migration Server resource for each workload, or allow the PlateSpin Migrate Connector to load-balance the migration jobs across all of the project’s available Migration Server resources of type PlateSpin Migrate.

With automated migration, imported workloads are automatically set to Automated Migration. You can set individual workloads separately. Automated Migration is disabled for a workload if the transformation method is not supported by automated migration.

  1. In the Web Interface toolbar, select Planning.

  2. Select the Workloads tab.

  3. Select the workload, then click Edit. You can alternatively double-click the workload of interest.

  4. On the Workload dialog in the Transformation Plan panel, click Edit.

  5. Do one of the following:

    • Migration Server: From the Migration Server list, select the Migration Server resource that you want to assign to the target workload.

    • Automated Migration: Select the Automated Migration check box to enable automatic assignment from among the available Migration Server resources that are of type PlateSpin Migrate.

  6. (Optional) Modify other Transformation Plan information as appropriate.

  7. Click Save, and then click Close.

  8. Click Close to exit the Workload dialog.