Launch the PlateSpin Migrate Web Interface.
If you have not configured a Hyper-V platform as a migration target, click Targets > Add Target, and then configure the target Hyper-V platform. See Table 18-6, Options for Hyper-V Target.
On the Workloads page, select the workload you want to configure.
Click Configure Migration.
Select one of the following based on the scope of data you want to transfer from the source to the target:
Full Replication: A full volume of data transfer takes place from the source to the target.
Incremental Replication: Only differences are transferred from the source to the target, provided they have similar operating system and volume profiles.
Depending on whether you want to perform full replication or incremental replication, do one of the following:
Full Replication: Select an existing Hyper-V target platform to which you want to migrate the source workload.
Incremental Replication: Select the target type as Virtual Targets. From the list of the prepared target workloads, select a virtual target workload that matches the source workload you want to migrate. If the prepared target workloads list is either empty or does not list a matching target workload, then click Prepare Workload to prepare the target workload to which you want to migrate the source workload.
Click Configure Migration.
Configure the following settings:
NOTE:All of the following settings are applicable for full replication of the workload. Some of the listed settings might not display or display differently when you configure incremental replication for the workload. For example:
The Virtual Machine Configuration Path setting does not display because a target workload matching the source workload must already be available to transfer only the differences from the source to this target.
The Volume Mapping setting displays the volumes and their mappings. You can edit the volume mappings.
Setting Name |
Description |
---|---|
Schedule Settings |
|
Incremental Recurrence |
Specify the following:
|
Full Replication |
Do one of the following:
NOTE:You must prepare the workload prior to the scheduled time.The full replication cannot run unless the target VM exists and the workload preparation is complete. Migrate skips the scheduled full replication and retries it at the next scheduled time. |
Blackout Window |
Use these settings to force a replication blackout. The replication blackout suspends scheduled replications during peak utilization hours or prevents conflicts between VSS-aware software and the PlateSpin VSS block-level data transfer component. To specify a blackout window, click Edit and do the following:
NOTE:The blackout start and end times are based on the system clock on the PlateSpin Server. |
Compression Level |
These settings control whether data is compressed during transmission between the source and target workloads, and the level of data compression applied.See Data Compression.Select one of the following options:
|
Bandwidth Throttling |
These settings control the bandwidth throttling. PlateSpin Migrate enables you to control the amount of available bandwidth consumed by direct source-to-target communication over the course of a workload migration. You can specify a throughput rate for each migration job. Throttling provides a way to prevent migration traffic from congesting your production network and to reduce the overall load of your PlateSpin Server. To throttle replications to a specified rate, specify the required throughput value in Mbps and the time pattern. |
Migration Settings |
|
Transfer Method |
(For Windows Workloads) Select a data transfer mechanism and security through encryption.See Supported Data Transfer Methods. To enable encryption, select the Encrypt Data Transfer option. See Security and Privacy. |
Source Credentials |
Specify the credentials required for accessing the workload. See Discovery Guidelines for Source Workloads. |
Number of CPUs |
Select the number of the CPUs. |
Virtual Machine Name |
Specify a display name for the new virtual machine. |
Configuration File Datastore |
Select a datastore associated with your VM for storing VM configuration files. |
Virtual Machine Configuration Path |
Specify the path to the configuration file on the target virtual machine. |
Storage Layout |
Specify the desired layout of data volumes (and volume groups) on the target workload disks:
|
Storage Options > Disks |
Specify the path to the hard disk on the target virtual machine. |
Storage Options > Volumes |
Select volumes to be included in the target for migration. For Windows file-based migrations, you can optionally adjust the size of the target volume by modifying the Size value in the row for that volume. NOTE:The ability to adjust the size of the target volume is not currently available in the Disk Layout view of storage in the Migrate Web Interface. See Cannot Adjust the Target Volume Size for File-Based Migrations in the Web Interface. |
NTFS Cluster Size |
(For File-Based Windows Workloads) Specify the cluster size for the NTFS volume. For information about the default cluster size for an NTFS volume, see the Microsoft Support KB Article 140365. |
Replication Network for Target |
Specify a network interface (NIC or IP address) on the target to use for replication traffic and select one of the following:
|
Replication Networks for Source |
Select one or more network interfaces (NIC or IP address) on the source to use for replication traffic. |
Services to Stop Before Any Replication |
We recommend that all the non-VSS compliant services or anti-virus are stopped temporarily on the source while the VSS snapshot is being captured on the source. Select the Windows services that you want to be temporarily stopped on the source workload while the VSS snapshot is being captured on the source. These services are restored as soon as the VSS snapshot creation completes. |
Services to Stop for Cutover with Replication |
Select the Windows services that should be permanently stopped on the source workload for cutover with any replication. The services stopped on the source workload during the replication process are not restored after cutover. The stopped services are restored after a Test Cutover. |
Boot Services to Disable on Target |
Select the boot services that you want to disable on the target workload. |
Target Workload Settings (These settings are applied during the Run Cutover) |
|
VM Memory |
Specify the amount of memory allocated to the target workload. |
Integration Services |
To install Hyper-V Integration Services on the target workload, select Install Integration Services. This option is selected by default. |
Hostname |
Do one of the following:
|
Domain / Workgroup |
Depending on whether the source workload belongs to workgroup or domain, one of the following displays:
Do one of the following depending on where you want the target workload to join:
|
Domain Credentials |
If you select Join Domain, specify the domain administrator credentials. |
Network Connections |
Select the local area connection and then select one of the following:
For Windows workloads that have more than one NIC, select the connection for each NIC. |
DNS Servers |
Specify the DNS Servers for the target workloads. This is applicable only if you select Static in the Network Connections option:
|
Services States on Target VM |
Select Windows services’ start conditions on the target VM. Start options are Automatic, Manual, Disabled, and Automatic (Delayed Start). |
Post-Migration Action |
Click Configure Action to select a previously configured custom action that you want to execute on your target workload as a part of the migration job. The command line parameters and timeout value that you previously configured for the selected action is displayed by default. You can edit these values as required. If you choose to timeout the action and have not specified any timeout value, then PlateSpin Migrate waits for a maximum period of 7200 seconds before timing out this action. For information about managing the post-migrations, see Managing Post-Migration Actions. |
Tag |
|
Tag |
Select a tag to assign to the workload. See Managing Workload Tags. |
(Optional) To change the target, click Change Target.
NOTE:If you change the target, all the settings you specified will be cleared.
Do one of the following:
Click Save to save the settings.
Click Save and Prepare to save the settings and start preparing the workload migration.
Click Cancel to exit.